City · California

ADU rules in Berkeley

5 sources

These are the primary sources for accessory dwelling unit regulations in Berkeley: the city's own zoning code, planning department pages, and permit guides. Start here before talking to anyone: the rules below are what your permit reviewer will apply.

Rules at a glance

Detached (backyard) ADU
Allowed

Detached ADUs are allowed with a ministerial Zoning Certificate on any lot in a district that permits housing and has an existing or proposed home or group living accommodation (fraternities, sororities and dormitories excepted). A lot with one single-family home may have one new-construction ADU (attached or detached), one conversion ADU and one JADU; a lot with an existing multifamily building may add up to 8 new-construction ADUs (never more than its existing units) plus interior conversions, a proposed multifamily building gets 2, and lots with more than one single-family home or a group living accommodation get 1. Table 23.306-2 sets 4-ft rear, interior-side and street-side setbacks and no front setback, and the city FAQ confirms an ADU may sit in the front setback. Table 23.202-1 marks ADUs 'NP' in the ES-R Environmental Safety-Residential district (Panoramic Hill), and the M, MM, MU-LI and M-RD manufacturing districts bar them; a state-exempt unit under Gov. Code 66323 must still be approved in any residential zone, as 23.306.040(A)(2) itself says.

BMC 23.306.020(A) and Table 23.306-1 (Ord. 7983-NS §§ 2, 4, 2025); Table 23.306-2; Table 23.202-1 (BMC 23.202.020); Table 23.206-1; BMC 23.306.040(A)(2)
Attached or internal ADU
Allowed

New-construction ADUs 'may be either attached or detached from the main building(s) and/or other ADUs, in any configuration' (Table 23.306-1 note 1), and an ADU counts as attached when it shares a wall with the main home. On a single-family lot an attached addition uses the one new-construction slot, while a conversion ADU (inside the house, a garage or an accessory building) and a JADU of up to 500 sq ft inside the home or its attached garage come on top. In duplexes and multifamily buildings, interior ADUs must be carved from non-habitable space such as basements, attics, garages and storage rooms. Outside the Hillside Overlay, multifamily lots may also add attached new construction, which Ord. 7983-NS (effective 10-9-2025) allowed after HCD's February 25, 2025 letter rejected the city's denial of an attached ADU on a duplex at 1902 Ward Street; inside the Hillside Overlay new ADUs on multifamily lots must be detached.

BMC Table 23.306-1 and note 1; BMC 23.306.030(A)(2) (Ord. 8007-NS § 14, 2026), (A)(4) and (B)(1)
Maximum size
1,200 sq ft outside the Hillside Overlay; inside it 850 sq ft (studio or 1 bedroom) or 1,000 sq ft (2+ bedrooms). Same caps for attached and detached, no percent-of-home cap, measured as gross floor area to the outside walls. JADU 500 sq ft. Height: 25 ft for new construction outside the hills; in the Hillside Overlay 20 ft detached and, attached, 25 ft or the existing building's limit, whichever is lower.

Conversions of existing space may exceed the cap and add up to 150 sq ft, and a converted accessory building keeps its nonconforming size and location (23.306.030(A)(1), (A)(3)). The caps are gross floor area measured 'within the outer surface of the main walls' (23.106.030), while Gov. Code 66321(b) sets the 850 and 1,000 sq ft floors in interior livable space; HCD's June 16, 2026 findings (item 6) told the city to switch, and where an outside-wall measurement would push a Hillside unit below the state floor, the state floor controls (Gov. Code 66325). Up to 800 sq ft of ADU and JADU area per lot is excluded from lot coverage and floor-area limits (23.106.020(B)(5), 23.106.030(B)(6)). The smaller Hillside caps and 20-ft detached height came with Ord. 7983-NS (adopted 9-9-2025, effective 10-9-2025), whose findings cite wildfire, Hayward Fault and evacuation risk; the city FAQ reads the attached Hillside limit as 20 ft for an addition, matching the overlay's 20-ft cap on residential additions (Table 23.210-1).

BMC Table 23.306-2 (Ord. 7983-NS § 5, 2025); BMC 23.306.030(A)(1), (A)(3) and (B)(1); 23.106.030(A) and (B)(6); 23.106.020(B)(5); Table 23.210-1; Gov. Code 66321(b) and 66325
Owner occupancy
Not required

No owner-occupancy requirement applies to ADUs; Gov. Code 66315 forbids one, and the city FAQ says an owner with an ADU does not have to live on site. For a JADU, the owner must live in the JADU or the main home only when the two share sanitation facilities, and never when the owner is a governmental agency, land trust or housing organization (23.306.040(C)(4) as restated by Ord. 8007-NS, effective 6-11-2026, matching Gov. Code 66333(b)). Owners holding an older recorded ADU Notice of Limitation from Berkeley's former owner-occupancy rule can apply to rescind and replace it with Zoning Officer approval and a $500 fee (city FAQ).

BMC 23.306.040(C)(4) (Ord. 8007-NS § 15, 2026); Gov. Code 66315 and 66333(b)
Extra parking
None. No off-street parking is required for any ADU or JADU, in any district.

Table 23.322-1 reads 'Junior ADU: None required / ADU: None required' for residential districts since Ord. 7983-NS § 12 (2025), and the commercial and manufacturing tables (23.322-2, 23.322-4) also say 'None required'. The Hillside Overlay rule requiring one space per unit on roadways narrower than 26 ft applies to main dwellings, not ADUs. Parking lost to an ADU need not be replaced (Gov. Code 66314(d)(11)); any parking an owner chooses to provide for an ADU, or as replacement for the main home, may go anywhere on the lot, including the front setback (23.322.080(G)).

BMC 23.322.030(A), Table 23.322-1 (Ord. 7983-NS § 12, 2025); Tables 23.322-2 and 23.322-4; BMC 23.322.080(G)
Approval process
Permitted use

ADUs and JADUs need a Zoning Certificate, reviewed with the building permit and approved or denied within 60 days of a complete application, with a written list of deficiencies on denial; there is no hearing, and the city says approved ADU permits are not appealable. Within 10 working days of submission, staff mail a courtesy notice to tenants on the lot and to owners and tenants of adjacent, confronting and abutting properties ($500 noticing fee, 23.306.040(B)). An ADU that is part of a project needing discretionary review waits for that approval (23.306.040(A)(1)), and the city FAQ says an Administrative Use Permit comes first when a conversion requires excavating within a nonconforming setback. The 15-business-day completeness clock of Gov. Code 66317(a)(2) applies directly even though the code omits it (HCD June 2026 finding 4).

BMC 23.306.040(A) (Ord. 7983-NS § 9, 2025) and 23.306.040(B); Gov. Code 66317
Rental restrictions
Long-term rental allowed; no rental shorter than 30 days (JADUs and state-exempt Gov. Code 66323 units must be rented for longer than 30 days). Short-term rentals (under 14 days) are barred in any ADU permitted after April 3, 2017. Separate sale only as a Chapter 21.29 ADU condominium (Gov. Code 66342 opt-in since 3-12-2026) or through a qualified nonprofit (66341); JADUs never. Rented ADUs are partially covered by the Rent Stabilization Ordinance (Rent Board registration and good-cause eviction, no rent ceiling) unless the ADU is the only one on an owner-occupied single-family lot.

The 30-day floor is written into a deed restriction recorded before the building permit issues (23.306.040(C)(3)); Gov. Code 66315 allows a 30-day minimum, but HCD's June 16, 2026 findings say a deed restriction may not be imposed on an ADU, and 66323(e) and 66333(g) require terms longer than 30 days for state-exempt units and JADUs. Chapter 23.314 allows short-term rentals only in the host's residence and only in ADUs permitted before April 3, 2017 that were never used for long-term rental; the city program requires a Short-Term Rental Zoning Certificate, a $451.25 application fee, 12% transient occupancy tax plus a 2% enforcement fee, and a 90-day yearly cap when the host is away. Ord. 7999-NS (adopted 2-10-2026, effective 3-12-2026) created a ministerial ADU condominium map process (at most 10 condominium units per lot, lienholder consent, no JADUs, and for a rented ADU not fully exempt from rent control the tenant's continued occupancy and a 90-day exclusive right to purchase). Under 13.76.050, ADUs created after June 30, 1980 are 'Partially-covered units' (no rent ceilings, but registration under 13.76.080 and good-cause eviction apply), while the single ADU on a single-family lot where the landlord lives is fully exempt for tenancies begun after November 7, 2018.

BMC 23.306.040(C)(2)-(3) and (D); BMC Ch. 21.29 (Ord. 7999-NS, 2026); BMC 23.314.020(A)(9), 23.314.040(D), 23.314.050(B); BMC 13.76.050(B)(1), (C)(6) and 13.76.080(A), (M); Gov. Code 66315, 66323(e), 66333(g), 66341, 66342
The fine print: 8 caveats that can change the picture
  • Gov. Code 66326(d) exposure: HCD's June 16, 2026 findings (ADU0008608) list six violations: single-family and multifamily lots must get the full Gov. Code 66323 allotment plus at least one 66314 unit, lots with several single-family homes must get the single-family 66323 allotment instead of one ADU, the code omits the 66317 completeness rules, ADUs may not be deed-restricted, and size caps must be stated in interior livable space. The response was due July 16, 2026; neither HCD's index (current to 7-14-2026) nor its dashboard (rows through 9-21-2026) shows one, and HCD's May 11, 2026 letter said the newest Berkeley ordinance on file was from 2023, so the 2025 and 2026 amendments may never have been submitted. Under 66326(d) (SB 9, effective 1-1-2026) an ordinance not submitted within 60 days, or whose findings go unanswered for 30 days, is null and void and the state standards apply (1,200 sq ft detached, 50 percent of the home for attached, no Hillside reductions). The city still administers Chapter 23.306 and is amending it rather than treating it as void.
  • Pending amendment: the 2026 ADU compliance ordinance (Planning Commission public hearing 10-7-2026, draft Resolution 2026-14; Council hearing not yet scheduled; to be sent to HCD within 60 days of adoption) would allow up to 3 ADUs plus 1 JADU on a single-family lot and 2 ADUs plus 1 JADU on lots with several single-family homes, add one ADU to the multifamily allowances (3 with a proposed multifamily building), restate the caps in interior livable space (new 23.106.045) without lowering the numbers, add a 15-business-day completeness review and a ZAB appeal, keep the deed restriction only for JADUs, move the ADU sale and 30-day rental rules into a new 23.306.040(E), and restore the Chapter 21.29 separate-sale exception. The Commission was also asked whether to cap the detached state-exempt unit at 800 sq ft instead. Re-verify after Council adoption.
  • Hillside Overlay ('-H' on the zoning map, the Berkeley hills): 850/1,000 sq ft caps instead of 1,200, a 20-ft height limit for detached ADUs, no projections into required ADU setbacks, and new ADUs on multifamily lots must be detached. Ord. 7983-NS grounds these limits in findings on wildfire, the Hayward Fault and evacuation (a July 15, 2025 city study estimated maximum ADU build-out could lengthen evacuation times by up to 102 percent). The 2022 Chapter 12.99 hillside ADU restrictions that HCD rejected on October 17, 2022 were repealed by Ord. 7888-NS (2023), and HCD's May 3, 2024 letter accepted that fix.
  • ES-R Environmental Safety-Residential district (Panoramic Hill): Table 23.202-1 lists ADUs as 'NP'. Gov. Code 66314(a) lets a city exclude areas for traffic and public-safety reasons, but 66323(a) requires ministerial approval of state-exempt units in any residential zone, so a 66323 unit there is likely approvable despite the table. ADUs are also not permitted in the M, MM, MU-LI and M-RD manufacturing districts (Table 23.206-1); MU-R and every commercial district allow them under Chapter 23.306.
  • Separate-sale codification trap: Ord. 7999-NS § 2 rewrote 23.306.040(C)(2) to allow separate sale 'under BMC 21.29 (ADU Condominium Ordinance)', through the qualified-nonprofit path, 'or as otherwise permitted by state law', but Ord. 8007-NS § 15 (adopted 5-12-2026, captioned as amending only (C)(4)) restated all of 23.306.040(C) from pre-2025 text, so the code now prints the old nonprofit-only wording. Chapter 21.29 remains in force, HCD's June 2026 letter quoted the Ord. 7999-NS wording, and the city's August 2026 FAQ says most ADUs may be sold as condominiums under Chapter 21.29; the pending amendment restores the exception.
  • City materials differ from the code on details: the ADU page still says the current standards 'went into effect on November 9, 2023' (Ord. 7888-NS), though the chapter was amended in 2025 and 2026; the FAQ and the STR page give the short-term-rental cutoff as ADUs built after April 1, 2017 (the code says permitted after April 3, 2017), and the STR page describes long-term rental use 'since April 1, 2007' where the code says any long-term rental before April 3, 2017. The ADU Information Sheet and FAQs PDF is the August 20, 2026 edition despite its 2023-11-07 file name.
  • Short-term rental definitions: Chapter 23.314 covers stays under 14 consecutive days, so rentals of 14 to 29 days fall outside the STR program but are still barred for deed-restricted ADUs by the 30-day minimum; guests staying 14 days or more may gain tenant protections under the Rent Stabilization Ordinance (city STR page).
  • State law chaptered in 2026, effective January 1, 2027 (caveats, not current values): AB 956 (Chapter 791, Statutes of 2026) amends Gov. Code 66323 to allow two detached new-construction ADUs on a single-family lot under the state-exempt pathway, with no JADU owed where two exist, more than Berkeley's one new-construction slot (the pending three-ADU allowance would cover it); it also extends the Civil Code 714.3 and 4751 limits on CC&R restrictions to any lot zoned for single-family use. SB 1117 (Chapter 809, Statutes of 2026) amends Gov. Code 66311.5 so impact fees on an ADU over 750 sq ft are charged only on the area above 750 sq ft; Berkeley's Land Use Planning Division assesses no ADU impact fees, though the school district charges developer fees on residential space over 500 sq ft (city FAQ).

Summarized from Berkeley's ordinance text, read October 2026; every row links the code section it came from. Rules often vary by zone and lot, so treat this as orientation, not a permit determination, and confirm with the planning department before you commit to a design.

Compare Berkeley with 119 nearby cities

ADU regulations

Short-term rental rules

Planning to rent your ADU on Airbnb or VRBO? Berkeley regulates short-term rentals separately; check these before counting on nightly rental income.

California statewide law also applies

California sets baseline ADU rights at the state level. Where local rules are stricter than state law allows, state law usually wins, so both are worth reading.

See California statewide rules

Spotted something outdated?

Zoning codes change. If a link is dead or Berkeley has updated its ordinance, report it and we'll verify against the official source.

Report a correction