City · California
ADU rules in Hemet
These are the primary sources for accessory dwelling unit regulations in Hemet: the city's own zoning code, planning department pages, and permit guides. Start here before talking to anyone: the rules below are what your permit reviewer will apply.
Rules at a glance
Detached ADUs are allowed with a proposed or existing home in every zone whose use table lists them: the R-R and R-1 single-family zones (the 'Secondary dwelling unit' row), the A-1 and A-2 agriculture zones and the R-2, R-3 and R-4 multiple-family zones, all as permitted (P) uses governed by Sec. 90-321. Since Ord. No. 2072 (adopted 3-10-2026) a single-family lot may carry up to two detached ADUs, one attached ADU and one JADU, provided the lot holds no more than four homes in total. Lots with an existing multifamily building may add up to four detached ADUs under the local text (never more than the number of existing units), but Gov. Code 66323(a)(4)(A)(ii) allows up to eight and controls through Hemet's own state-law-prevails clause (Sec. 90-321(e)). A detached unit of 800 sq ft or less with 4 ft side and rear setbacks is the state-exempt type the city must approve ministerially.
Hemet Municipal Code § 90-321(a)(4), (c)(2), (c)(3)(a)-(b), (e) (Ord. No. 2072, § 2, adopted 3-10-2026); use matrices §§ 90-183, 90-312, 90-383; Gov. Code § 66323(a)(2), (a)(4)Attached ADUs, including conversions of space inside the home or an attached garage, are allowed on the same lots as detached units (Sec. 90-321(c)(2)); a single-family lot may have one attached ADU plus one JADU inside the home. A JADU (150 to 500 sq ft, entirely within a single-family home) is limited to one per lot and may add up to 150 sq ft only for its entrance (Sec. 90-321(d)(1), (d)(4)). On existing multifamily buildings, up to 25 percent of the unit count (at least one) may be attached ADUs, and up to 25 percent (at least one) may be created by converting non-livable space such as storage rooms or garages. Approval is a ministerial building plan check with no hearing.
Hemet Municipal Code § 90-321(c)(2), (c)(3)(a)(2)-(3), (c)(3)(b)(2)-(3), (d)(1), (d)(4) (Ord. No. 2072); Gov. Code § 66323(a)(1), (a)(3)Hemet caps both attached and detached ADUs at the lowest ceilings state law permits: 850 sq ft of interior livable space for a studio or one-bedroom unit and 1,000 sq ft for two or more bedrooms, measured net of exterior walls and garages (Sec. 90-321(b), (c)(5)-(6)). An attached ADU that enlarges the home by more than 150 sq ft is also held to 50 percent of the existing home's floor area, but Gov. Code 66321(b)(3) bars a percentage cap that blocks an 800 sq ft unit; a detached unit built on the state-exempt (simplified) path is capped at 800 sq ft, and a JADU at 150 to 500 sq ft. Conversions of existing space under Gov. Code 66323(a)(1) carry no state size cap even though the local attached cap reads as covering them. Heights: 16 ft for a one-story detached ADU (18 ft within half a mile of a major transit stop or high-quality transit corridor, plus 2 ft for a roof pitch matching the house), 25 ft for a two-story detached ADU over a garage that keeps 10 ft from abutting single-family lots (reducible to accessory-structure setbacks) and meets the second-story privacy rules of Sec. 90-315(g), and 25 ft and two stories (or the zone's lower limit) for an attached ADU.
Hemet Municipal Code § 90-321(b), (c)(5), (c)(6), (c)(15), (c)(16), (d)(7) (Ord. No. 2072); Gov. Code §§ 66321(b)(2)-(4), 66323(a)(1)-(2)Hemet imposes no owner-occupancy requirement on ADUs, consistent with Gov. Code 66315. For a JADU, the owner must live in the main home or in the JADU only when the JADU shares sanitation facilities with the house; a JADU with its own bathroom, or one owned by a public agency, land trust or housing organization, needs no owner on site (Sec. 90-321(d)(5), matching Gov. Code 66333(b) as amended by SB 543 and AB 1154). Every JADU needs a recorded deed restriction before its certificate of occupancy (no separate sale, size limit), while an ADU needs one only if it is to be sold separately under state law (Sec. 90-321(c)(13)).
Hemet Municipal Code § 90-321(c)(13), (d)(5) (Ord. No. 2072); Gov. Code §§ 66315, 66333(b)Sec. 90-321(c)(8) says no parking is generally required for ADUs or JADUs, but the city 'may' require one space per detached ADU or per bedroom, whichever is less, which can be tandem on the driveway or in a setback area. No space can be required when the ADU is within half a mile walking distance of public transit, in a designated historic district, part of the house or an existing accessory structure, where on-street permits are required but not offered, within one block of a car-share vehicle, or applied for together with a new home on the lot (the six Gov. Code 66322(a) cases). A garage, carport or uncovered space demolished or converted for the ADU need not be replaced, and a state-exempt detached unit of 800 sq ft or less cannot carry a parking condition under Gov. Code 66323(b). The code does not say when the city uses the 'may' option, so confirm with Planning for a larger detached unit more than half a mile from a bus stop.
Hemet Municipal Code § 90-321(c)(8)(a)-(c) (Ord. No. 2072); Gov. Code §§ 66314(d)(10)-(11), 66322(a), 66323(b)ADU and JADU applications go to the Building Department for building plan check and 'shall be permitted ministerially without discretionary review or public hearing' when they meet Sec. 90-321 and the building and health codes (Sec. 90-321(a)(1)-(2)). The city must decide completeness within 15 business days and review resubmittals only for the listed items, and an application not acted on within 60 days is deemed approved; denials come with a full written list of deficiencies. Plans are submitted through the Building and Safety online portal. The city has no pre-approved ADU plan program yet (still a Planning Commission future agenda item on 10-6-2026, although AB 1332 (2023) required one by 1-1-2025), and its 2023 ADU Plan Check Guide still says a Planning Commission conditional use permit may be required for ADUs that miss the standards, which the current ordinance does not provide.
Hemet Municipal Code § 90-321(a)(1)-(2) (Ord. No. 2072); Gov. Code §§ 66316, 66317Sec. 90-321(a)(2)(c) says an ADU or JADU 'may not be used for short-term rentals' and, if rented, must be rented for a term longer than 30 days; Gov. Code 66323(e) and 66333(g) set the same rule for state-exempt units and JADUs, while for an ordinary ADU it is one day stricter than the 30-days-or-longer term Gov. Code 66315 lets cities require (Sec. 90-321(c)(16) repeats the state wording). Hemet's short-term lodging law separately excludes ADUs: Ord. No. 2075 (adopted 4-28-2026, replacing the 2025 Ord. No. 2060 version still printed in the code) defines a lodging unit as a dwelling unit and states that an accessory dwelling unit is not one, so no short-term lodging permit can be issued for an ADU. An ADU may be rented separately from the main home but sold separately only where state law allows (the Gov. Code 66341 qualified-nonprofit path); Hemet has not adopted a Gov. Code 66342 condominium ordinance. The rental registration program was repealed in 2021 (Ord. No. 1970), but the Chapter 18 business license covers the rental of any dwelling or part of one (Sec. 18-44).
Hemet Municipal Code § 90-321(a)(2)(c), (c)(1), (c)(16) (Ord. No. 2072); § 18-701 as repealed and replaced by Ord. No. 2075 (adopted 4-28-2026); § 18-44; Gov. Code §§ 66315, 66323(e), 66333(g), 66341, 66342The fine print: 13 caveats that can change the picture
- Operative text: Sec. 90-321 as repealed and restated by Ord. No. 2072 (Zoning Ordinance Amendment 25-003; introduced 2-24-2026, adopted 3-10-2026 by 5-0, effective 30 days after passage), codified in Municode Supp. No. 69, Update 2. No later ordinance through the 9-29-2026 City Council and 10-6-2026 Planning Commission agendas touches it.
- HCD: the only ADU letter is the 10-8-2025 technical assistance repeal request (ADU0006784; HCD had only Hemet's 2018 ordinance on file); HCD records a city response committing to amend by February 2026, and Ord. No. 2072 followed; HCD has issued no findings on Ord. No. 2072 (dashboard read 2026-10-07, newest statewide ADU letter 9-23-2026). No public record shows Ord. No. 2072 reaching HCD within 60 days (Gov. Code 66326(a)); if it did not, Gov. Code 66326(d) would void it and the state standards would apply, including a 1,200 sq ft detached cap (Gov. Code 66314(d)(5)).
- Hemet's own clause (Sec. 90-321(e)) lets state law override several Ord. No. 2072 limits: the four-unit cap on detached ADUs at existing multifamily buildings (state: up to eight, Gov. Code 66323(a)(4)(A)(ii)); the 16 ft height tied to those units (state allows 18 ft on a lot with a multistory multifamily building, 66321(b)(4)(C)); the 850/1,000 sq ft cap as applied to conversions of existing space (66323(a)(1)); and the 50 percent cap on attached additions where it would block an 800 sq ft unit (66321(b)(3)).
- Impact fees: Sec. 90-321(c)(12) waives impact fees only for ADUs 'less than 750 square feet' and charges proportional fees from 750 sq ft, while Gov. Code 66311.5 exempts units of 750 sq ft or less, so a unit of exactly 750 sq ft is fee-exempt under state law. SB 1117 (Ch. 809, Stats. 2026, effective 1-1-2027) limits fees on larger units to the area above 750 sq ft, replacing the proportional formula in Sec. 90-321(c)(12)(b).
- AB 956 (Ch. 791, Stats. 2026, effective 1-1-2027) amends Gov. Code 66323 to allow two detached new-construction ADUs on a single-family lot on the state-exempt path, with no JADU owed where two exist; Hemet already allows two detached ADUs per single-family lot within a four-home total, so the change mainly moves the second unit onto the state-exempt track. Re-read on 1-1-2027.
- Sec. 90-321(c)(10) still requires architectural compatibility based on 'architectural style, construction materials, and primary color' even though the ZOA 25-003 staff reports said this subjective standard had been eliminated; Gov. Code 66314(b)(1) limits local ADU standards to objective ones and 66323(b) bars any unlisted standard on state-exempt units.
- Street dedication: Sec. 66-2 (Ord. No. 2064, 10-14-2025) requires an irrevocable offer of right-of-way dedication for any addition to, or alteration of, an existing single-family home or habitable accessory structure regardless of size (which reads onto attached ADUs and conversions), and street improvements when a project adds 50 percent or more to a structure's floor area. Whether the city applies it to ADUs is undocumented; HCD's 9-1-2026 technical assistance letter to Anaheim says Gov. Code 66315, 66317(c) and 66319 bar road dedication and construction conditions on ADUs.
- Zone gaps: the SLR Small Lot Residential zone's use lists (Secs. 90-502, 90-503) omit ADUs, the commercial-zone mixed-use rows (Sec. 90-893) are conditional uses with no ADU row, and Sec. 90-312 treats unlisted uses as not permitted; Sec. 90-321(a)(4) and Gov. Code 66323(a) still require ministerial approval in residential and mixed-use zones. Specific plan and planned community areas carry their own use lists.
- Legacy definitions in Sec. 90-4 still describe a 'granny flat' as an ADU for one or two occupants aged 62 or older and a 'guesthouse' as quarters without a kitchen, and the single-family use table labels the ADU row 'Secondary dwelling unit (e.g., guest house or granny flat)'; Sec. 90-321 carries no age limit and Gov. Code 66315 bars added standards.
- The city's ADU Plan Check Guide (DocumentCenter 8918, a March 2023 file still linked from the Standard Plans page) predates Ord. No. 2072 and says a Planning Commission conditional use permit may be required for ADUs that do not meet development standards; the ordinance and Gov. Code 66317 provide only ministerial review, so the guide is not curated. Hemet has no ADU information page.
- Short-term rentals: Ord. No. 2075 (adopted 4-28-2026) repealed and replaced Chapter 18, Article XVIII and invoked the SB 346 Short-Term Rental Facilitator Act; Municode still prints the Ord. No. 2060 (6-24-2025) version until the next supplement, and both versions exclude ADUs from short-term lodging permits.
- SB 9 lot splits: a parcel created by an SB 9 urban lot split may hold no more than two units, ADUs and JADUs included, and the two parcels no more than four (Sec. 90-321(c)(3)(c)). Lots in the Hemet-Ryan Airport Influence Area stay subject to the Riverside County Airport Land Use Compatibility Plan (Sec. 90-312 preamble); the county ALUC found ZOA 25-003 consistent with the 2017 Hemet-Ryan plan.
- Re-check: the next Municode supplement (codifying Ords. No. 2073 to 2083, including No. 2075); the HCD dashboard for any findings on Ord. No. 2072; adoption of a pre-approved ADU plan program; 1-1-2027 for SB 1117 and AB 956.
Summarized from Hemet's ordinance text, read October 2026; every row links the code section it came from. Rules often vary by zone and lot, so treat this as orientation, not a permit determination, and confirm with the planning department before you commit to a design.
ADU regulations
- library.municode.comOfficial sourceVerified October 2026Code of Ordinances §90-321https://library.municode.com/ca/hemet/codes/code_of_ordinances?nodeId=CO_CH90ZO_ARTXISIMIREZO_S90-321ACDWUN
- mcclibraryfunctions.azurewebsites.usOfficial sourceVerified October 2026https://mcclibraryfunctions.azurewebsites.us/api/ordinanceDownload/12521/1417864/pdf
Short-term rental rules
Planning to rent your ADU on Airbnb or VRBO? Hemet regulates short-term rentals separately; check these before counting on nightly rental income.
California statewide law also applies
California sets baseline ADU rights at the state level. Where local rules are stricter than state law allows, state law usually wins, so both are worth reading.
See California statewide rulesSpotted something outdated?
Zoning codes change. If a link is dead or Hemet has updated its ordinance, report it and we'll verify against the official source.
Report a correctionReady to build?
Planning an ADU in Hemet?
Tell us about your project and we'll match you with vetted local designers and builders as we bring them online. No cost, no obligation.