ADU rules in Monterey County

5 sources

These are the primary sources for accessory dwelling unit regulations in Monterey County: the county's own zoning code, planning department pages, and permit guides. Start here before talking to anyone: the rules below are what your permit reviewer will apply.

Unincorporated areas only

County zoning applies only outside city limits. If your property is inside a city or town, that municipality's own ADU ordinance governs instead, even though it sits within Monterey County.

Find your city's rules in California

Rules at a glance

Detached (backyard) ADU
Allowed

Detached ADUs are allowed with an existing or proposed home in every unincorporated zone that allows single-family or multifamily dwellings: inland under Title 21 Sec. 21.64.030, and in the coastal zone under Title 20 Sec. 20.64.030 in the HDR, MDR, LDR, RDR, WSC, CGC, MLC, VSC, CAP and AC districts (the county's 12 cities, including Salinas and Monterey, set their own rules). Inland, the 2020 ordinance bars full-size ADUs in resource-constrained areas (B-8 overlays, the North County Planning Area outside the Castroville Community Plan, the first-home-only parts of the Toro and Greater Salinas planning areas, and Specific Plan areas), where only the state-mandated detached unit of up to 800 sq ft, 16 feet tall with 4-foot side and rear setbacks, is allowed (21.64.030.C.1-C.2.a). In the coastal zone, Ord. 5432 (effective December 19, 2025) removed the old North County ban, the Carmel-area 40-acre minimum and the Big Sur 50-unit cap, but ADUs remain prohibited in the Big Sur Critical Viewshed (20.64.030.E.10). Both codes allow one ADU plus one JADU beside a single-family home, and lots with an existing multifamily building may add up to eight detached ADUs (never more than the existing unit count) under the coastal code and Gov. Code 66323(a)(4), which overrides the inland text's limit of two. Everywhere, a unit served by a private well, septic system or a water system of 2 to 199 connections needs Environmental Health approval and is prohibited if water or sewage disposal is inadequate (21.64.030.E.2; 20.64.030.D.1).

Monterey County Code § 21.64.030.C, C.1-C.2, E.2-E.3 (Ord. 5341, 2020); § 20.64.030.C.1, D.1, E.1, E.10 (Ord. 5432, eff. Dec. 19, 2025); Gov. Code §§ 66314(a), 66323(a)
Attached or internal ADU
Allowed

Attached ADUs (additions sharing a wall with the house, which in the coastal zone may not have internal circulation with it, 20.64.030.E.7) and conversions of space inside an existing or proposed home or an existing accessory structure, with up to 150 sq ft added for entry and exit, are allowed under both codes; in the inland resource-constrained areas only the state-mandated conversion inside the house or an accessory structure, with exterior access, is allowed (21.64.030.C.2.b). One JADU of up to 500 sq ft inside a single-family home is allowed ministerially everywhere inland, including where new ADUs are otherwise barred (21.64.030.E.1), and in the listed coastal zones with an efficiency kitchen, a separate entrance and, if it shares a bathroom, an interior entry to the house (20.64.030.F.1, F.6-F.8). Existing multifamily buildings may convert non-livable space such as storage rooms, attics, basements or garages into ADUs for up to 25 percent of the building's units (20.64.030.E.1.b; Gov. Code 66323(a)(3), which controls over the inland text's 25-percent-of-floor-area wording under 21.64.030.D). Units previously permitted as senior citizen or caretaker units count as ADUs, and permitted guesthouses may be converted (21.64.030.C.3-C.4; 20.64.030.C.3-C.4).

Monterey County Code § 21.64.030.C.2.b, C.3-C.4, D, E.1, E.3; § 20.64.030.C.3-C.4, E.1.b, E.7, F.1-F.8; Gov. Code §§ 66323(a)(1), (a)(3), 66333
Maximum size
1,200 sq ft (1,000 sq ft in the Big Sur coast and coastal B-8 areas); JADU 500 sq ft; inland resource-constrained areas limited to the state-exempt 800 sq ft detached unit or conversions; coastal in-home conversions capped at 50% of the house; detached height 16 ft (18 ft on multifamily lots or near transit, plus 2 ft for a matching roof pitch)

Inland, every ADU is capped at 1,200 sq ft and every JADU at 500 sq ft (21.64.030.E.9-E.10; the 21.06.372 definition repeats the 1,200 sq ft limit), and because the ordinance applies the state ADU standards 'as may be amended' (21.64.030.D), an attached ADU is also held to 50 percent of the existing home under Gov. Code 66314(d)(4), never below the 800 sq ft interior-livable-space unit that 66321(b)(3) protects. In the inland resource-constrained areas a new detached ADU may not exceed 800 sq ft and 16 feet, and a converted unit may add only 150 sq ft for entry and exit (21.64.030.C.2). In the coastal zone new attached and detached ADUs, and conversions of accessory structures built after March 25, 2024, are capped at 1,200 sq ft in the Carmel Area, North County and Del Monte Forest land use plan areas and at 1,000 sq ft in the Big Sur Coast area and any B-8 combining district, while a conversion of space inside an existing house may not exceed 50 percent of it (20.64.030.E.4); site coverage and floor-area limits may never block an 800 sq ft unit with 4-foot setbacks (E.6). Detached units may be 16 feet tall beside a single-family home and 18 feet on a multifamily lot, or 18 feet (20 feet with a roof pitch matching the house) within half a mile walking distance of a major transit stop or high-quality transit corridor, taller only with a Coastal Development Permit or, inland, a Zoning Administrator Use Permit; attached units follow the zone's height limit (20.64.030.E.2; 21.64.030.E.5; Gov. Code 66321(b)(4)). The coastal 50 percent cap on in-home conversions goes beyond what Gov. Code 66323(b) allows for state-exempt conversions, a conflict HCD has not raised.

Monterey County Code §§ 21.06.372, 21.64.030.C.2, D, E.5, E.9-E.10 (Ord. 5341); § 20.64.030.E.2, E.4, E.6, F.4 (Ord. 5432); Gov. Code §§ 66314(d)(4)-(5), 66321(b), 66323(a)-(b)
Owner occupancy
Not required

Neither code requires the owner to live on a lot with an ADU, and Gov. Code 66315 bars such a requirement. For JADUs, the coastal code still requires the owner to live in the house or the JADU unless the owner is a government agency, land trust or housing organization (20.64.030.F.10), but since January 1, 2026 Gov. Code 66333(b), as amended by AB 1154, allows owner occupancy only where the JADU shares sanitation facilities with the house, and 66339.5 makes the state JADU article control over conflicting local text; the inland code has no JADU owner clause of its own and applies state JADU law (21.64.030.C.2.b.iv, D). In practice a JADU with its own bathroom carries no owner-occupancy requirement anywhere in the unincorporated county, while one that shares the home's bathroom does. A deed restriction recorded before the building permit bars separate sale of a JADU and fixes its size and attributes (20.64.030.F.9; Gov. Code 66333(c)).

Monterey County Code § 20.64.030.F.9-F.10 (Ord. 5432); § 21.64.030.C.2.b.iv, D (Ord. 5341); Gov. Code §§ 66315, 66333(b)-(c) (AB 1154, eff. Jan. 1, 2026), 66339.5
Extra parking
None, except 1 space per ADU on a few coastal Carmel Point lots mapped in CIP Appendix 15 (where the home's own required parking must also stay); JADUs never

Inland, no parking is required for an ADU or JADU: the Sec. 21.58.040 parking table has listed 'ADU/JADU Not Required' since Ord. 5341 (2020). In the coastal zone no off-street parking is required for an ADU and no replacement parking is required when a garage, carport or other covered parking is converted or removed, except on lots inside the areas mapped in Coastal Implementation Plan Appendix 15, 'ADU Parking Required', where each ADU needs at least one off-street space and all other on-site parking requirements must still be met (20.64.030.E.5; the 20.58.040 table points to both). The Coastal Commission's report describes Appendix 15 as a handful of lots along the seaward edge of the Carmel Point neighborhood, where street parking serves Carmel Beach and Carmel River State Beach, and as the only place in the county with on-site ADU parking; that beach-access rule departs from Gov. Code 66314(d)(11) and 66322 but stands under the Coastal Act savings clause of 66329(a). JADUs never need parking (20.64.030.F.5).

Monterey County Code § 21.58.040 (Ord. 5341 § 3); §§ 20.58.040, 20.64.030.E.5, F.5 (Ord. 5432) and Coastal Implementation Plan Part 6, Appendix 15; Coastal Commission staff report F13b (Oct. 10, 2025), Exhibit 4; Gov. Code §§ 66314(d)(10)-(11), 66322(a), 66329(a)
Approval process
Permitted use

Inland, an ADU or JADU needs only a construction (building) permit approved ministerially: the county applies state ADU law, including the Gov. Code 66317 ministerial 60-day process (21.64.030.D), JADUs are expressly ministerial (E.1), and the county's FAQ says an ADU is generally an allowed use inland, though Design Approval in 'D' overlay districts, tree removal or other factors may apply; only an ADU that exceeds both the zone's height rules and 16 feet needs a Use Permit from the Zoning Administrator (E.5). In the coastal zone an ADU or JADU needs a Coastal Administrative Permit processed under Chapter 20.76 with no required public hearing and a decision within 60 days of a complete application, unless it is attached to or inside an existing single-family house and not somewhere 14 CCR 13250 requires a permit (20.64.030.G.1-G.2); Design Approval by the Chief of Planning applies in 'D' districts and is not appealable (D.3), and other project parts (ESHA, slopes over 30 percent, archaeological sites, extra height) can require a Coastal Development Permit, often with a hearing (G.3). Since October 10, 2025 Gov. Code 66329(c) makes the coastal ADU decision unappealable to the Coastal Commission. Environmental Health water and sewer clearance, and in the Cal-Am area an MPWMD water permit, come before the construction permit issues.

Monterey County Code § 21.64.030.D, E.1, E.5 (Ord. 5341); § 20.64.030.D.3, G.1-G.3 (Ord. 5432); Ch. 20.76; County ADU Plans and Info page FAQ (Sept. 2026); Gov. Code §§ 66317, 66329(a), (c) (AB 462, eff. Oct. 10, 2025)
Rental restrictions
Long-term rental allowed (terms over 30 days; 90 days or more in the Big Sur coastal area); ADUs and JADUs can never be vacation rentals; no separate sale except qualified-nonprofit sales (Gov. Code 66341); no condo opt-in

ADUs and JADUs may be rented separately for terms over 30 days: the inland code allows rentals 'for more than thirty (30) days' and bars use as a vacation rental of 30 consecutive days or less (21.64.030.E.4), and the coastal code requires 31 consecutive calendar days or longer (20.64.030.D.2), consistent with Gov. Code 66315, 66323(e) and 66333(g). In the Big Sur coastal planning area the certified Land Use Plan (Policy 5.3.3, amended with the October 10, 2025 LCP amendment) prohibits renting an ADU or any part of one for less than 90 days. Separately, the county's vacation rental license law allows vacation rentals only in single-family dwellings and prohibits them in ADUs and JADUs, and a guesthouse cannot be rented apart from the house (Sec. 7.120.040.U, operative October 14, 2024). ADUs cannot be sold separately from the home except by a qualified nonprofit under Gov. Code 66341 (20.64.030.E.11; the inland flat ban yields under 21.64.030.D), and the county has adopted no Gov. Code 66342 condominium ordinance.

Monterey County Code §§ 21.64.030.E.4 (Ord. 5341), 20.64.030.D.2, E.11 (Ord. 5432), 7.120.040.U (Ord. 5424); Big Sur Coast Land Use Plan Policy 5.3.3 (Res. 25-426; LCP-3-MCO-25-0034-1-Part A); Gov. Code §§ 66315, 66323(e), 66333(g), 66341, 66342
The fine print: 17 caveats that can change the picture
  • Scope: unincorporated Monterey County only (Carmel Valley, Pebble Beach, Big Sur, Prunedale, Castroville, Moss Landing and the other unincorporated communities). The county's 12 cities set their own ADU rules; Salinas and the City of Monterey have their own directory entries.
  • Two codes: inland areas follow Title 21 Sec. 21.64.030 (Ord. 5341, adopted Sept. 15, 2020), which applies state ADU and JADU law 'as may be amended' with state law controlling any conflict (21.64.030.D); the coastal zone follows Title 20 Sec. 20.64.030 as restated by Ord. 5432 (adopted Nov. 18, 2025, effective Dec. 19, 2025, after the Coastal Commission certified LCP-3-MCO-25-0034-1-Part A as submitted on Oct. 10, 2025) plus the amended Big Sur Coast, Carmel Area and North County Land Use Plans. The inland update (REF240015) has had no hearing; the Board's June 23, 2026 order on Referral 2026.07 says a companion document for inland areas will be introduced soon.
  • Inland resource-constrained areas (21.64.030.C.1): B-8 overlay areas, the North County Planning Area outside the Castroville Community Plan, the first-home-only parts of the Toro and Greater Salinas (north of Salinas) planning areas, and Specific Plan areas allow only what state law mandates: one detached new ADU of up to 800 sq ft (16 ft, 4-ft setbacks) or a conversion inside a house or accessory structure, plus a JADU. County growth limits and unit caps do not apply to ADUs or JADUs (21.64.030.C.1; 20.64.030.C.2), and the North County coastal buildout cap of 2,043 units excludes them (20.64.180.G.1).
  • Coastal limits: ADUs are prohibited in the Big Sur Critical Viewshed (20.64.030.E.10); size caps are 1,200 sq ft in the Carmel Area, North County and Del Monte Forest plan areas and 1,000 sq ft in Big Sur and B-8 areas; in-home conversions are capped at 50 percent of the house; North County coastal ADUs and JADUs require water-efficient fixtures and drought-tolerant landscaping on the whole lot (20.64.030.D.4); and a Chief of Planning Design Approval applies where a 'D' district is combined.
  • State-law conflicts with no HCD finding yet. Coastal text: the one-ADU limit on single-family lots (20.64.030.E.1.a) is narrower than Gov. Code 66323(a), which allows a converted ADU, a JADU and a detached 800 sq ft ADU in combination; the 50 percent cap on in-home conversions (E.4.c) is not a standard 66323(b) authorizes for state-exempt conversions; the universal JADU owner-occupancy clause (F.10) yields to 66333(b) and 66339.5. Inland text: the limit of two detached ADUs on multifamily lots (versus eight under 66323(a)(4)(A)(ii)), the 'visually consistent and compatible' design rule (versus the objective-standards rule of 66314(b)(1)) and the flat ban on separate sale (versus 66341) are resolved by the ordinance's own clause that state law controls (21.64.030.D).
  • Big Sur 90-day rental minimum: Big Sur Coast LUP Policy 5.3.3, certified Oct. 10, 2025, prohibits renting an ADU or any part of one for less than 90 days, while Title 20 elsewhere requires 31 days or longer and Gov. Code 66315 lets an agency require only rental terms of 30 days or longer; a public comment in the Coastal Commission packet quotes HCD's Aug. 26, 2024 letter to San Marino calling a 90-day minimum inconsistent with state law. The Commission approved it under the Coastal Act, which 66329(a) preserves; treat it as the county's operative rule in Big Sur, but legally contestable.
  • Coastal parking exception: one off-street space per ADU, with the house's own required parking kept, applies only on the few Carmel Point parcels mapped in Coastal Implementation Plan Appendix 15, 'ADU Parking Required' (Exhibit 4 of the Coastal Commission report); it is a Coastal Act beach-access rule that departs from Gov. Code 66314(d)(11) and 66322 but stands under 66329(a).
  • Coastal permitting in practice: the Coastal Administrative Permit needs no public hearing by code (20.64.030.G.2) and cannot be appealed to the Coastal Commission (Gov. Code 66329(c), since Oct. 10, 2025), yet 2026 staff reports for ADU-only permits still describe a noticed administrative decision that is 'referred to the Monterey County Zoning Administrator if a public hearing is necessary' and appealable to the Planning Commission (AP 26-055, June 17, 2026). Only ADUs attached to or inside an existing single-family house can be exempt, and never where 14 CCR 13250 requires a permit (ESHA, highly scenic areas, within 50 feet of a bluff edge, well or septic work).
  • Water is the binding constraint. ADUs on private wells, septic systems or water systems of 2 to 199 connections need Environmental Health approval and are prohibited if water or sewage disposal is inadequate (21.64.030.E.2; 20.64.030.D.1), and the county notes that most septic lots under 1.25 acres need an alternative treatment system. In the unincorporated area served by California American Water within the Monterey Peninsula Water Management District, the county's June 2026 Board report says the Cease and Desist Order still prohibits new water meters, and an ADU needs an MPWMD water permit plus a county allocation under the Water Allocation Policy adopted June 9, 2026 (Res. 26-178), which reserves water for ADUs and JADUs using 0.12 acre-feet a year or less (25.46 AFY remained for ADUs, JADUs and single-family homes on July 27, 2026).
  • Ord. 5451 (adopted Sept. 1, 2026, effective Oct. 1, 2026) amends Chapter 15.06 so an ADU served by a water system or private well that fails primary drinking water standards may use point-of-use or point-of-entry treatment, provided every dwelling on the property installs a device, Environmental Health approves it and a deed notification is recorded; it was not yet on Municode (the ordinance bank ended at Ord. 5446 on Sept. 29, 2026).
  • Short-term rentals: the vacation rental regime (Title 7 Ch. 7.120 operation licenses, inland Sec. 21.64.290 operative Oct. 14, 2024, coastal Sec. 20.64.290 effective Oct. 24, 2025) never allows ADUs or JADUs (7.120.040.U). After Monterey County Vacation Rental Alliance v. County of Monterey (Case No. 24CV004922) the county suspended enforcement of its resident-only homestay and individual-owner provisions, and on Jan. 6, 2026 the Board (3-2) directed amendments banning vacation rentals in residential zones; drafts went to the Planning Commission on Feb. 11, 2026 and were still under development in September 2026. Every version keeps ADUs and JADUs ineligible.
  • Separate sale: only qualified-nonprofit sales under Gov. Code 66341 (written into 20.64.030.E.11; the inland flat ban yields under 21.64.030.D); the county has not opted into Gov. Code 66342 ADU condominiums.
  • HCD: no ADU technical assistance or findings letter to Monterey County appears in HCD's letter index (current to July 14, 2026) or its dashboard (queried Sept. 29, 2026); the May 11, 2026 ADU letter indexed as 'MONTEREY' is addressed to the City of Monterey. HCD issued the county a Notice of Violation on May 28, 2026 over its still-noncompliant 6th cycle housing element, which does not change ADU rules. Whether the county submitted Ords. 5341 and 5432 to HCD is not public; an unsubmitted ordinance would be void under Gov. Code 66326(d), leaving the state standards alone.
  • Stale county pages: the ADU Plans and Info page links the coastal ordinance to an obsolete Municode node (nodeId ending 20.64.030REACDWUN; the current section node ends 20.64.030REACDWUNJUACDWUN), and the permit-center Short Term Rentals page still says coastal vacation rental rules await Coastal Commission certification, which came Aug. 13, 2025.
  • Pre-designed plans: the county offers three free detached ADU plans (515, 749 and 1,200 gross sq ft, in two styles) that still go through normal construction-permit review; the three-bedroom plan owes impact fees, and the Board's June 23, 2026 order says the plans are being updated to the 2025 building code.
  • 2026 state law: SB 1117 (Chapter 809, Statutes of 2026) and AB 956 (Chapter 791, Statutes of 2026) were signed on September 29, 2026 and take effect January 1, 2027. From that date AB 956 amends Gov. Code 66323 so the state-exempt pathway allows two detached new-construction ADUs on a single-family lot, with no JADU owed where two exist, and extends the Civ. Code 714.3 and 4751 CC&R anti-restriction rule to any lot zoned to allow single-family use; SB 1117 amends Gov. Code 66311.5 so impact fees on an ADU over 750 sq ft are charged only on the area above 750 sq ft. From January 1, 2027 the two-unit exempt count widens the gap with the coastal one-ADU limit; until then the current text governs.
  • Re-verify by 2027-03-31: the inland ADU update (REF240015) promised in the June 23, 2026 Board order and Housing Element Program H-2.A; the vacation rental amendments (REF250042 coastal, REF250043 inland); Municode codification of Ord. 5451; and any HCD review of Ord. 5432.

Summarized from Monterey County's ordinance text, read September 2026; every row links the code section it came from. Rules often vary by zone and lot, so treat this as orientation, not a permit determination, and confirm with the planning department before you commit to a design.

Compare Monterey County with 119 nearby cities

ADU regulations

Short-term rental rules

Planning to rent your ADU on Airbnb or VRBO? Monterey County regulates short-term rentals separately; check these before counting on nightly rental income.

California statewide law also applies

California sets baseline ADU rights at the state level. Where local rules are stricter than state law allows, state law usually wins, so both are worth reading.

See California statewide rules

Spotted something outdated?

Zoning codes change. If a link is dead or Monterey County has updated its ordinance, report it and we'll verify against the official source.