County · California
ADU rules in San Bernardino County
These are the primary sources for accessory dwelling unit regulations in San Bernardino County: the county's own zoning code, planning department pages, and permit guides. Start here before talking to anyone: the rules below are what your permit reviewer will apply.
Unincorporated areas only
County zoning applies only outside city limits. If your property is inside a city or town, that municipality's own ADU ordinance governs instead, even though it sits within San Bernardino County.
Find your city's rules in CaliforniaRules at a glance
Detached ADUs are allowed across the unincorporated county wherever a home is allowed: the land use tables list 'Accessory dwelling unit' as A (allowed use, no planning permit required) in the RL, RS and RM residential districts, the RC and AG resource and agriculture districts, CR (Rural Commercial) and SD-RES, always accessory to a residential use on the same site, and not at all in FW, OS or the other commercial and industrial districts. Chapter 84.36, added by Ord. 4504 (adopted January 13, 2026, effective February 12, 2026), defines a detached unit as one physically separated from the primary dwelling (a detached ADU larger than the existing home is deemed the primary dwelling), and Table 84-0 allows up to two ADUs of any type on a single-family lot, three on lots of five acres or more, with 4-foot side and rear setbacks and a 5-foot separation from other buildings. Separately, 84.36.080(b)(2) approves by right one new detached ADU of up to 800 sq ft of livable space with 4-foot side and rear setbacks, combinable with a JADU (Gov. Code 66323(a)(2)); multifamily lots may add up to eight detached ADUs (never more than the existing unit count) or two with a proposed multifamily building.
San Bernardino County Code Title 8 (Development Code) §§ 84.36.040(a)(2), 84.36.070 and Table 84-0 (notes 2-3), 84.36.080(b)(2), (b)(4); Tables 82-4, 82-7, 82-11, 82-17 (§§ 82.03.040, 82.04.040, 82.05.040, 82.06.040), all as added or amended by Ord. 4504; Gov. Code §§ 66314, 66323(a)(2), (a)(4)Attached and internal ADUs are allowed on the same lots: 84.36.040(a)(1) and (a)(3) authorize units attached to the side, top or below the primary dwelling and conversions of existing space in the home or an accessory structure (basement, attic, attached or detached garage, shed, storage area), including an old home converted to an ADU when a larger new primary dwelling is built (still capped at 1,200 sq ft). Attached units count toward the same two-ADU aggregate (three on five acres or more) and are capped at 50 percent of an existing primary dwelling and 1,200 sq ft, while conversions of existing space have no size cap and no setback or height requirement. 84.36.080(b)(1) approves by right one converted ADU and one JADU per lot within the proposed or existing space of the home or an accessory structure (up to 150 sq ft of expansion for ingress and egress), and on multifamily lots at least one ADU and up to 25 percent of the existing unit count may be built in non-livable space. A JADU (up to 500 sq ft of interior livable space, entirely within a single-family residence, one per lot) is allowed in the same districts as ADUs.
SBCC §§ 84.36.030(c), 84.36.040(a)(1), (a)(3), (b), (c), 84.36.070 Table 84-0 (notes 7-8), 84.36.080(b)(1), (b)(3) (Ord. 4504); Gov. Code §§ 66314(d)(3)-(4), 66323(a)(1), (a)(3), 66333Table 84-0 in 84.36.070 caps attached and detached ADUs at 1,200 sq ft of livable space, and with an existing primary dwelling an attached ADU may not exceed 50 percent of that dwelling (note 7), but note 1 guarantees an ADU of up to 800 sq ft of livable space with 4-foot side and rear setbacks whatever the table's other limits. Conversions of existing space carry no maximum (a converted former primary dwelling stays capped at 1,200 sq ft under 84.36.040(a)(3)), JADUs are capped at 500 sq ft of interior livable space, and the minimums are 200 sq ft for ADUs and 150 sq ft for JADUs, never barring an efficiency unit. Heights are 18 feet for detached units plus 2 feet where the roof matches the primary dwelling's pitch and 25 feet for attached units, never more than two stories, with no height or setback limit for conversions built within existing dimensions. These limits meet or exceed the state floors of Gov. Code 66321(b) as amended by SB 543 (850 sq ft, or 1,000 sq ft with more than one bedroom, of interior livable space; 16-foot detached height) and match the 1,200 sq ft default of 66314(d)(5). HCD's September 18, 2026 findings letter on the county ordinance lists size among its topics and is not public; its roughly October 18, 2026 response deadline has passed with no amendment or readoption on the Board or Planning Commission record, so if the county also sent HCD no written response, Gov. Code 66326(d) voids Chapter 84.36 and the state standards apply instead (still a 1,200 sq ft detached cap and 50 percent of the home for attached units, but without the county's height and design rules; see caveats).
SBCC § 84.36.070 and Table 84-0 (Unit Size, Building Height; notes 1, 5-8, 10-11), §§ 84.36.030(c), 84.36.040(a)(3) (Ord. 4504); former § 84.01.060(d) (Ords. 4383, 4400); Gov. Code §§ 66314(d)(4)-(5), 66321(b), 66326(d)No for ADUs: 84.36.060(b) states that owner occupancy shall not be required for an accessory dwelling unit, as Gov. Code 66315 requires. For a JADU the owner must live in the main home or the JADU only when the JADU shares sanitation facilities with the main home; the requirement falls away when the JADU has its own bathroom or the owner is a governmental agency, land trust or housing organization, tracking Gov. Code 66333(b) as amended by AB 1154 effective January 1, 2026. Every JADU needs a deed restriction recorded with the County Recorder that bars separate sale and fixes the unit's size and attributes. Ord. 4504 narrowed the former 84.01.060(c)(2), which required JADU owner occupancy regardless of sanitation.
SBCC § 84.36.060(b) (Ord. 4504); former § 84.01.060(c)(2) (Ords. 4383, 4400); Gov. Code §§ 66315, 66333(b)-(c)Table 84-0 requires one uncovered off-street space for each ADU on single-family and multifamily lots alike, which may be tandem on a driveway (note 12), and none for a JADU. Under 84.36.080(a)(3) the requirement does not apply to a JADU, to an ADU within one-half mile walking distance of public transit, in a historic district listed on the National or State Register or the county registry, within the proposed or existing primary dwelling or a converted accessory structure, where on-street permits are required but not offered to the occupant, within one block of a car-share vehicle, or when filed together with a new primary or multifamily dwelling on a lot meeting one of those tests; a garage, carport or covered parking structure removed or converted for an ADU never needs replacement. Gov. Code 66314(d)(10)(A) caps ADU parking at 'one parking space per accessory dwelling unit or per bedroom, whichever is less', so on a plain reading a studio ADU with no bedroom owes no space, while Table 84-0 asks one space of every unit; the December 18, 2025 staff report shows Ord. 4504 left the one-space rule unchanged, and HCD's September 18, 2026 findings letter on the ordinance lists parking among its topics. If the ordinance is void under Gov. Code 66326(d) for want of a timely response (unsettled; see caveats), only the state ceiling of one space per unit or per bedroom, whichever is less, with the 66322 exemptions, would apply. Table 84-0 does not expressly exempt the 800 sq ft by-right detached unit of 84.36.080(b)(2), but Gov. Code 66323(b) bars any standard that section does not authorize (it authorizes none on parking) and 84.36.080(b) approves those units notwithstanding anything to the contrary.
SBCC § 84.36.070 Table 84-0 (Parking and Loading; note 12), § 84.36.080(a)(3), (b) (Ord. 4504); Gov. Code §§ 66313(m), 66314(d)(10)(A), (d)(11), 66322(a), 66323(b), 66326(d)The land use tables list ADUs and JADUs as A, an allowed use needing no planning permit, in every district that allows them, and 84.36.050(a) says an ADU or JADU permit is considered and approved ministerially, without discretionary review or hearing, notwithstanding the need for a variance or special use permit. Land Use Services must decide completeness within 15 business days (15 more after a resubmittal) and approve or deny within 60 days of a complete application where a primary or multifamily dwelling exists, or within 30 days for a detached unit built from a county pre-approved plan; the 60 days may be delayed for a concurrent new-home application or at the applicant's written request (84.36.050(b), tracking Gov. Code 66317 as amended by SB 543). Before a permit issues the applicant needs written sewer availability or Environmental Health approval of a septic system (holding tanks are barred), water district or well approval, fire authority sign-off and county approval of drainage, ingress and egress (84.36.050(f)-(i)); units in the Floodplain Safety overlay must meet Chapter 82.14. The county posts pre-approved detached ADU plan sets on its Building and Safety handouts page.
SBCC § 84.36.050(a)-(b), (f)-(k) (Ord. 4504); Tables 82-4, 82-7, 82-11, 82-17 (key: A = allowed use, no planning permit required); Gov. Code §§ 65852.27, 6631784.36.060(a) lets an ADU or JADU be rented separately from the primary dwelling in all regions for terms longer than 30 consecutive days, and JADU rentals must always run longer than 30 days (Gov. Code 66333(g)). An ADU may be rented for 30 days or less only in the Mountain and Desert Regions, only with a short-term residential rental permit under Chapter 84.28 (listed as SUP, Special Use Permit, in the land use tables), and not if it was built under the 84.36.080(b) by-right exemptions, which state law holds to terms longer than 30 days (Gov. Code 66323(e)); Chapter 84.28 applies only in the Mountain and Desert Regions and the county's STR program says short-term rentals are only allowed there, so Valley Region ADUs are long-term only. STR permits are issued per dwelling unit, at most one per parcel under 2 acres and two on parcels of 2 acres or more, at most two per owner, are not transferable and carry transient occupancy tax, so on a parcel under 2 acres the house and the ADU cannot both be short-term rentals. Separate sale or conveyance of any ADU is prohibited except as authorized under what the ordinance prints as 'Section 66431' (a misprint for the Gov. Code 66341 qualified-nonprofit path); the county did not opt into a Gov. Code 66342 ADU-condominium ordinance, although a public comment at the December 18, 2025 Planning Commission hearing asked it to.
SBCC § 84.36.060(a), (c) (Ord. 4504); §§ 84.28.010, 84.28.020, 84.28.040(a)-(c); Tables 82-4, 82-7 (Short-Term Residential Rentals: SUP); Gov. Code §§ 66315, 66323(e), 66333(g), 66341, 66342The fine print: 13 caveats that can change the picture
- Scope: this entry covers only the unincorporated Valley, Mountain and Desert regions administered by San Bernardino County Land Use Services. The incorporated cities apply their own ADU ordinances, including the directory's separate entries for Chino, Fontana, Hesperia, Ontario, Rancho Cucamonga, Rialto, San Bernardino, Upland and Victorville.
- Unit count conflict (both texts): Table 84-0 allows two ADUs of any type on a single-family lot (three on five acres or more) plus one JADU, but 84.01.050(a), as amended by Ord. 4504, allows only 'a combination of two' of an ADU, a JADU and a guest house on parcels under five acres (three at five acres or more), and the December 18, 2025 staff report describes the limit as 2 units on lots under 5 acres. Gov. Code 66323(a) (last amended by SB 543) requires ministerial approval of 'any combination' of a converted ADU plus a JADU and one new detached ADU of up to 800 sq ft, which is three units on any single-family lot. State law controls: 84.36.080(b) approves the by-right units 'notwithstanding anything to the contrary' and 84.36.090 lets the Director waive any inconsistent provision and apply state law. HCD's September 18, 2026 findings letter on the ordinance is tagged 'unit allowance', so this is likely among its findings.
- Regional and overlay rules: in the Fire Safety (FS) overlay, which covers the wildfire risk areas of the mountains, valley foothills and desert region (82.13.030), Table 84-0 note 9 imports Chapter 82.13, whose 82.13.050(o) requires exterior wall separations of at least 10 feet between buildings and interior side yards of 20 percent of lot width (5 to 15 feet) unless alternate hazard protection measures are approved under 82.13.090, more than the 4-foot side and rear setback that Gov. Code 66314(d)(7) allows for a new ADU; the CBC Chapter 7A and CRC exterior wildfire construction standards named in 82.13.050(b) and fire authority sign-off (84.36.050(h)) also apply. In a Floodplain Safety overlay the ADU must meet Chapter 82.14 (84.36.050(k)); Ord. 4516 (adopted June 23, 2026, effective July 23, 2026, not yet codified) exempts qualifying conversions of existing permitted structures in a Shaded X Zone from the one-foot elevation rule.
- Septic and wells: 84.36.050(f)-(g) require written sewer district confirmation or Environmental Health approval of an existing or new septic system and of any well, and bar holding tanks; Table 84-0 note 13 calls for an Advanced Treatment System designed to accommodate each added dwelling, subject to Environmental Health approval, where the property is under one-half acre with an existing primary residence; the utility connection exemption for conversions does not apply on lots served by both a septic system and a private well (84.36.080(a)(2)). The May 2026 county handout adds that sewer connection is required within 200 feet of a sewer line (plus 100 feet per dwelling unit) and that a percolation test up to 5 years old (10 if recertified) may be required, as Gov. Code 66323(f) permits.
- Zone standards and lot size: 84.36.070(a)(1) makes ADUs comply with all development standards of the zoning district, and Table 84-0 leaves lot size, width, depth and lot coverage to the zone (RL allows 20 percent coverage in every region). Gov. Code 66314(b)(1) bars minimum lot size requirements for ADUs and 66321(b)(3) bars coverage, floor area, front setback or lot size limits that would block an 800 sq ft ADU with 4-foot side and rear setbacks, which Table 84-0 note 1 also guarantees.
- Definition trap: the Development Code's general definition (810.01.030(f), last amended by Ord. 4383 in 2020 and untouched by Ord. 4504) says roofs must be at least ten feet apart for an ADU 'to be considered detached', while Table 84-0 sets a 5-foot minimum separation and 84.36.040(a)(2) treats any physically separated unit as detached; 84.36.030 says the chapter's definitions supplement Gov. Code 66313, which prevails where they conflict and defines an ADU as attached or detached with no separation distance. A unit 5 to 10 feet from the house could be classed as attached (and held to the 50 percent cap) by a reviewer reading 810.01.030(f).
- Guest houses are a separate use (84.01.050(a)(3)): they count toward the two-unit accessory cap, need one uncovered parking space (Table 83-15), must sit at least ten feet from the primary dwelling, and may not be rented or used as a separate dwelling except as a permitted short-term rental under Chapter 84.28.
- HCD review status: HCD's Technical Assistance and Enforcement Letters dashboard (queried October 5 and October 23, 2026) lists an Accessory Dwelling Unit Law 'Ordinance Findings Letter' to San Bernardino County dated September 18, 2026 (case ADU0009128), meaning HCD found that the county's ADU ordinance, Ord. 4504, does not comply with state ADU law in some respects. HCD has not posted the letter (the dashboard still says to contact HCD for a copy), so its individual findings are not public; the dashboard tags it front setback, JADU, parking, unit allowance, size and fire sprinklers, topics that match Table 84-0's front setback, size and parking rows, the two-unit cap in 84.01.050(a) and Table 84-0, and the sprinkler rule in 84.36.080(a)(1). The dashboard cannot show whether the county answered: its response column prints the same 'Contact HCD for the response' text for every letter, including letters HCD's own index marks as answered.
- Response deadline and possible fallback to state law: Gov. Code 66326(b) gave the county no more than 30 days, to about October 18, 2026, to respond, and then to amend the ordinance or readopt it unchanged by a resolution with findings explaining why it complies. Under 66326(d) (SB 9, 2025), an ordinance whose agency 'fails to respond to the department's findings ... within 30 days' is null and void, and the county must then apply the state standards of Gov. Code 66310 et seq. directly until it adopts a compliant ordinance. The deadline has passed with no amendment to Chapter 84.36 or 84.01.050 and no readopting resolution on the Board of Supervisors agendas of September 22, October 6 and October 20, 2026 or the Planning Commission agendas of September 3 and 17 and October 8, 2026 (the October 22 meeting was cancelled), but a written staff response to HCD would satisfy the 30-day rule without appearing in any public record, so whether the ordinance is void is unsettled. If it is, the state standards also cap a detached ADU at 1,200 sq ft and an attached one at 50 percent of the home, and cap parking at one space per unit or per bedroom, whichever is less, while the county-specific rules in this entry (the unit caps, heights, setbacks and design limits) would stop applying as written; ask Land Use Services which text it is applying. Whether the county submitted Ord. 4504 to HCD within 60 days of adoption (by March 14, 2026) is also unconfirmed.
- Drafting and codification artifacts in the adopted text: 84.36.060(c) cites 'Section 66431 of the Government Code' (a Subdivision Map Act section) where the nonprofit conveyance rule is 66341; 84.36.050(d) cites 66332(a), which SB 543 renumbered to 66311.7 effective January 1, 2026; the codified 84.36.080(b)(2) and (b)(4) print '§ 66321(4)(b)(A), (B), or (C)' for the ordinance's 66321(b)(4)(A)-(C); and Table 84-0 note 1 reads 'rear year setbacks'. The Word 'Final' ordinance on the county's Legistar item omits 84.36.070(a)(2)-(3), which the signed ordinance and the American Legal codification both contain. The Title 8 table of contents still lists 84.01.060 with a dead link although Ord. 4504 removed that section.
- Stale and superseded county copies: the directory's stored March 2023 handout URL now redirects to the county home page, and the county still hosts pre-2026 handouts (for example LUS-ADU-Handout-UPDATED-3323-1.pdf) describing the repealed 84.01.060 rules. The Building and Safety handouts page links the February 13, 2026 edition, and the March 20, 2026 edition remains online; both match the May 2026 edition's rules (the editions differ only in the date line, a footnote marker and the JADU attached height cell, 25 ft versus N/A).
- 2026 state law: SB 1117 (Chapter 809, Statutes of 2026) and AB 956 (Chapter 791, Statutes of 2026) were signed on September 29, 2026 and take effect January 1, 2027. From that date AB 956 amends Gov. Code 66323 so the state-exempt pathway allows two detached new-construction ADUs on a single-family lot, with no JADU owed where two exist, and extends the Civ. Code 714.3 and 4751 CC&R anti-restriction rule to any lot zoned to allow single-family use; SB 1117 amends Gov. Code 66311.5 so impact fees on an ADU over 750 sq ft are charged only on the area above 750 sq ft. Until then the current text governs, and the unit-count and fee notes in this entry describe the pre-2027 rules.
- Re-verify by mid-December 2026: check HCD's dashboard and letter folder for a posted copy of the September 18, 2026 findings or a follow-up letter (a notice of violation or Attorney General referral under 66326(c) would signal that the county did not respond), the Board's Legistar record for an amendment to Chapter 84.36 or 84.01.050, American Legal for a supplement past S-45 (codifying Ords. 4516 and 4522 and anything later), and the January 1, 2027 start of AB 956 and SB 1117.
Summarized from San Bernardino County's ordinance text, read October 2026; every row links the code section it came from. Rules often vary by zone and lot, so treat this as orientation, not a permit determination, and confirm with the planning department before you commit to a design.
ADU regulations
- codelibrary.amlegal.comOfficial sourceVerified October 2026https://codelibrary.amlegal.com/codes/sanbernardino/latest/sanberncty_ca/0-0-0-198937
- lus.sbcounty.govOfficial sourceVerified October 2026https://lus.sbcounty.gov/wp-content/uploads/sites/48/ADU-Handout-May2026.pdf
- lus.sbcounty.govOfficial sourceVerified October 2026https://lus.sbcounty.gov/planning-home/handouts/
Short-term rental rules
Planning to rent your ADU on Airbnb or VRBO? San Bernardino County regulates short-term rentals separately; check these before counting on nightly rental income.
California statewide law also applies
California sets baseline ADU rights at the state level. Where local rules are stricter than state law allows, state law usually wins, so both are worth reading.
See California statewide rulesSpotted something outdated?
Zoning codes change. If a link is dead or San Bernardino County has updated its ordinance, report it and we'll verify against the official source.
Report a correctionReady to build?
Planning an ADU in San Bernardino County?
Tell us about your project and we'll match you with vetted local designers and builders as we bring them online. No cost, no obligation.